Search
  • A+
  • A-

Current & Future Projects


Project Description 
2020 Village Crack Filling Program The proposed 2020 Crack Filling Map can be found here.  Work will primarily be in the area east and north of Manitowoc Rd this year.  If funding allows, other segments shown on the map will be targeted.

Work was completed in May 2020
Manitowoc Road (Allouez Ave to Kewaunee Rd/
Hwy 29) 
Sanitary and Water Main (C-20)
 
Sanitary and watermain utility work is planned to begin September 28, and run through mid November.

The roadway will be closed to through traffic for the duration of the project. Daytime delays are expected.

Traffic may be limited to 1-lane with flagging operations during the workday. The intersection of Manitowoc Road with Allouez Ave will remain open with some delays expected.

No detour will be posted. Through traffic is advised to use Main St (US 141).

At times, residents and business customers within the project limits will need to use the nearest side road to and from their destination, including Klondike Rd, Willow Rd, and Ontario Rd.

 

As part of the project the Village will repair sanitary laterals in the road right-of-way and assess this work back to the property owner per our assessment policy.  Residents that have leaking sanitary laterals on their property should have these replaced. 
Guns Street
County JJ (Verlin Rd) to Green bay limits
2021
Project to include water and sanitary replacement, storm sewer and inlet repairs, street resurfacing, sidewalk construction and street trees.

Guns Street was recently awarded Wisconsin DOT Local Road Improvement funding for $450,000 towards the roadway improvements for this project.

Properties that have sanitary laterals in need of repair have been mailed notices. Responses are requested by November 1st. The Village will repair laterals in the road right-of-way and assess this work back to the property owner per our assessment policy.

Utility and road work in planned for late spring through early fall, 2021. The roadway assessment hearing will be held around February 2021.
Village Street Resurfacing

This map is the Village's current street construction program for 2020-2024. The Village Board approves the capital improvement plan each year.

Any streets shown on the Capital Improvement Program may move forward or back in construction year based on roadway needs and funding available.

A list of Frequently Asked Questions is also available for viewing regarding Village construction and assessments.

2021 Resurfacing Program (update 7/22/20)

Streets expected in the 2021 resurfacing program include the following:

Moonrise Ct (all)
Guns St (County JJ to Green Bay limits)
Steffens Ct (may be 2022)

2023 Resurfacing Program (update 7/22/20)
Streets expected in the 2023 resurfacing program include the following:

Bluebill St (Mallard to Oriole)
Mallard St (Verlin to Skyview)
Oriole St (Verlin to Skyview)
Skyview St (all)
Lucerne Ct (all)
Vail Ct (all)
Blue Spruce Ct (all)
Blue Spruce Dr (Juneberry to Blue Moon)
Blue Moon (Eaton Rd to Blue Spruce Dr)
Verlin Rd (Bellevue St to Lime Kiln)
Eldorado Dr (all)
Seville Dr (all)

 Manitowoc Road roadway project (Allouez Ave. to Kewaunee Rd.) 2021
The Village will be making improvements to Manitowoc Road from Allouez Ave to Kewaunee Rd. Design is complete as of August 1st 

Real estate acquisition is now complete. Most acquisitions are temporary limited interests to allow for proper grading of the properties abutting the roadway.

Private utilities will be moved in the summer and fall of 2020. WPS will be moving overhead power poles. Tree trimming may be required for this work.

Roadway Construction is scheduled for 2021, including sidewalk installation.  A realignment of the Ontario Road approaches to Manitowoc Road is planned to provide a safer and more efficient intersection.

A Public Informational Meeting was conducted on 9/21/17. 
 Sidewalk Improvements  Sidewalk Map

Construction dates on the map are subject to change.
Steffens Ct - sanitary and roadway improvements (2021) The sanitary sewer that runs under I-43 and Steffens Ct is in need of upsizing to accommodate future growth in the NE area of the Village.  Steffens Ct also is in need to pavement repair.  These two projects are planned to be done together the second half of 2021.

Upcoming Events

No events available.